Author: danny

9
Sep

2022

Norfolk

RAF Neatishead, Norfolk – Removal of two Radar Masts – April 2021 Think Lifting were tasked to plan and remove two redundant radar masts from inside a secure RAF facility in Norfolk. A 60t crane was used for lifting the mast, with a high level boom to sling each item and for the burners to […]

9
Sep

2022

Sandwich Kent

The removal of two redundant chimney stacks at the Pfizer complex near Sandwich. Both chimneys were part of a demolished energy centre, where we had previously hand removed a genset and associated equipment on another visit. These were the last two items to come down on site. We used a 220t crane and a high […]

6
Sep

2022

O2 Arena

Think Lifting Ltd were pleased to be a part of the massive team effort, lead by the DE Group, to get the O2 Arena back open after it was damaged by storms. A huge clear up operation took place with Think Lifting using a cherry picker alongside a team of skilled abseilers on the roof, […]

22
Aug

2019

Kemsley Paper Mill

Removal of a 72m high Steel Chimney at Kemsley Paper Mill in Sittingbourne Kent. A 450t Crane was used to lift the Chimney down in 4 sections.

15
Mar

2019

Leicester Square

Install of Transformers, Thermal Stores and AHU’s. Lowered down 6 floors, via an electric chain hoist, into the basement of the new Edwardian Hotel in Leicester Square, London.

17
Dec

2018

Robertsbridge

Removal of a Footbridge using a 180t Crane at the British Gypsum Site in Robertsbridge.

17
Dec

2018

Dungeness

Install of a Water Treatment Plant at Dungeness ‘A’ Nuclear Power Station, to filter out contaminates as part of the Decommissioning Programme. A 90t Crane & 40t Crane Tandem Lift, to upright 2 x 10t Tanks as part of the Install, as well as all the associated Equipment.  

29
Oct

2018

Enfield

Install of a 16t Metal Press using a Gantry Crane and a 25/35 Versa Lift in Enfield.

29
Oct

2018

North London

Install of two 20t Engines in a North London Energy Centre, including the off-load and install of the Exhaust and Heat Exchangers.

24
Aug

2018

Cranbrook Energy Centre

Cranbrook Energy Center in Exeter. 350t and 60t Cranes used to lift 15t / 20m high Chimney down through the roof.